Preparatory work at the Jawor factory construction site is moving ahead on schedule. Work on road surface hardening and preparing the construction office infrastructure has concluded. Electrical and water supply lines have been connected and modular containers and controlled access gates have been installed. In November, work will focus on fencing off the entire construction site and developing its external infrastructure: access roads, parking lots and underground utility systems. Simultaneously, construction crews are conducting earthworks and reinforcement and cement works for the foundations of the factory’s main building. This work is scheduled to be completed in early December.